Updates on Ettalong Channel dredging program

Latest update

14 November 2018

The dredge is currently working in the navigation channel opposite Lobster Beach, with dredging around 60% complete. Weather permitting the dredge will continue for the remainder of this week and work is expected to be completed next week.

About the dredging program

Ettalong channel

The marked navigational entrance channel—known as Ettalong channel—to Brisbane Water generally follows close to the eastern foreshore from Wagstaffe Point, Lobster Beach and Little Box Head.

From time to time, maintenance dredging of the channel is required due to the dynamic nature of the entrance sand shoals and sand movement.

On 21 May 2018, the government announced further emergency dredging to reinstate navigational access particularly for the public ferry service on the basis that Central Coast Council had committed to apply for matching funding under the Rescuing our Waterways Program.

This emergency program is now being implemented by the NSW Department of Industry—Lands & Water and NSW Roads & Maritime Services. A larger collaborative dredging program led by council will seek to use dredged sand to mitigate the impact of coastal hazards and improve beach amenity.

The emergency dredging program ensures boating access for larger vessels is reinstated in the interim period.

Current dredging plan

Stage one and two of the emergency dredging program at the ocean end of the Ettalong Channel has been completed with the removal of around 20,000 cubic metres of sand to provide a channel 60 metres wide and 2.5 metres deep.

On completion of stage one and two of the emergency dredging program, an inspection of the channel identified the need for additional dredging adjacent to Lobster Beach.

On 1 November 2018 additional dredging of the navigational channel adjacent to Lobster Beach commenced. It is anticipated this work will provide a channel 30 metres wide and 2.5 metres deep.

Previous dredging

Previous planned maintenance was undertaken in 2010 in partnership by the state and local government.

Emergency dredging of the channel was completed by the NSW Government in June, July and October 2017 with the dredging providing temporary relief for boaters including the ferry service.